|
Bleaching and Dyeing of Cotton Knitted
Fabric
|
Product Code
|
: |
248100009 |
| Quality and
Standards |
: |
As per IS
689:1956, IS 763:1957,
IS 786:1957, IS 687:1966, IS 3417:1966 |
| Uploaded on |
: |
January 2006 |
Introduction
Bleaching of textile grey fabrics
is generally carried out to impart whiteness to textile
fabrics by removing natural colouring matter. The process
of dyeing is carried out to improve the marketability
of textile products and also to suit the customer needs
by adding colour. These two processes are generally
carried out in open tank, kier machines, jet dyeing
machines, jiggers, soft flow dyeing machines etc. For
hosiery goods, it is carried out with winch machines,
since it imparts very less tension during operation.
Viable processing units can be set up as most of the
fabric manufacturing units do not have their own processing
units. In this report, details are provided for setting
up the unit for bleaching and dyeing of cotton knitted
fabrics.
Market Potential
The demand for hosiery garments
is increasing due to its popularity in domestic and
export market. There are number of units engaged in
manufacturing of knitted cloth and most of these units
are not having their own captive processing units. Bleaching
and dyeing of knitted fabric produced by these units
are normally carried out from outside on paying requisite
processing charges. It is, therefore, presumed that
setting up of textile processing units is economically
viable.
Basis and Presumptions
This project is based on single
shift basis with 300 working days in a year. Time period
for achieving maximum capacity utilisation is considered
from 3rd year from the date on which production is started.
Rental value of the building is taken at Rs. 2 per sq.
ft. Costs of machinery and equipments/materials indicated
refer to a particular make and approximately to those
prevailing at the time of preparation of this project.
Cost of installation and electrification
is taken @ 10% of cost of machinery and equipment. Non-refundable
deposits, project report cost, trial production, security
deposit with Electricity Board are classified under
pre-operative expenses.
Depreciation has been considered
at 10% on plant and machinery, 15% on office furniture,
fixtures, vehicle and 20% on testing equipments. Interest
rate on capital loan has been taken @ 12% per annum.
Implementation Schedule
The implementation period required
for executing this project right from selection of site
to starting the trial run production will be 6 months.
Technical Aspects
Process of Manufacture
The knitted fabric to be bleached
is thoroughly wet in a soap solution of 2% and piled
in kier boiling pan containing 1.5% caustic soda, 2%
soda ash and 1% lisapol etc. and allowed to boil for
6-8 hours. The cloth is washed well and taken to SS
winches for bleaching using 2% bleaching powder and
then washed thoroughly. This bleached cloth is scoured
using hydrochloric acid of 1.5% concentration. After
sometime, cloth is washed thoroughly to neutralise the
traces of acid. In case of only bleaching the cloth
is treated with optical whitening agent, thereafter,
it is hydro-extracted, dried and calendered as final
operations.
In case of dyeing, about 15-20%
salts, 2% brightol C paste, 2-4% dyes as per shade are
mixed and fabric is treated with the solution in winches.
The cloth is allowed to run for several times in order
to maintain uniform shade, thereafter, washed, hydro-extracted,
dried and calendered.
Production Capacity (per annum)
| |
Quantity (Kg.) |
Value (Rs.) |
| 1. Bleaching Charges |
4,50,000 |
1,15,86,000 |
| 2. Dyeing Charges |
4,50,000 |
1,48,05,000 |
|
Total
|
9,00,000 |
2,63,91,000 |
Motive Power
50 HP is required to run the unit
and proposed to be obtained from State Electricity Board.
Pollution Control
As this process involves treatment
of chemicals, entrepreneurs are required to obtain NOC
from State Pollution Control Board.
Energy Conservation
Energy can be conserved by proper
house-keeping i.e. unnecessary running of boilers, heaters
and fans are to be monitored in order to reduce the
excess energy consumption.
Technical Aspects
A. Fixed Capital
| (i) Land and
Building |
|
| (i) Land 4000 Mtrs.
@ Rs. 3000 per Sq. Mtr |
Rs.1,20,00,000
|
| Boundary wall and
gates |
Rs. 5,00,000 |
| Factory shed 400
Sq. Mtr, @ Rs. 6000 / Sq. Mtr |
Rs. 24,00,000 |
| Raw Material &
finished goods storage 500 Sq. Mtr@ Rs. 6000 / Sq.
mtr. |
Rs. 30,00,000 |
| Office Building
300 Sq. Mtr @ 750 / Sq. Mtr |
Rs. 22,50,000 |
| Workers sitting
hall 500 Sq.Mtr @ Rs.6000/Mtr |
Rs. 30,00,000 |
| |
Rs.1,18.00,000 |
| Utility plants
area e.g., bore well, raw water storage, boiler,
generator and effluent treatment plant 200 Sq. Mtr
@ Rs. 6000/Sq. Mtr |
Rs. 12,00,000 |
|
Total
|
Rs 2,43,00,000 |
(ii) Machinery and Equipments
| Sl. No. |
Description |
No. |
Rate (Rs.) |
Amount (Rs.) |
| 1. |
SS Winch m/c of
6-4× 8×6 200kg. |
1 |
4,00,000 |
4,00,000 |
| 2. |
SS Winch m/c 6-4'×
6×6 size 150kg. |
3 |
2,00,000 |
6,00,000 |
| 3. |
MS Kier wall thick
1/4' bottom 8' |
2 |
1,50,000 |
3,00,000 |
| 4. |
Steam callendering
m/c roller sizes 51/21 |
1 |
3,00,000 |
3,00,000 |
| 5. |
Hydro-extractor
40-45 kg capacity |
2 |
2,50,000 |
5,00,000 |
| 6. |
4 cylinder drier
with motor and gear box |
1 |
7,00,000 |
7,00,000 |
| 7. |
S.S. Conveyors
with ball bearing |
4 |
50,000 |
2,00,000 |
| 8. |
Baby boiler with
storage tank chimney, water softening plant |
1 |
8,00,000 |
8,00,000 |
| 9. |
Water softening
plant (cap. 6kl/hr), with storage tank pumps and
S.S. piping |
1 |
7,00,000 |
7,00,000 |
| 10. |
Effuent treatment
plant |
1 |
5,00,000 |
500,000 |
| 11. |
Steam pipeline
and other accessories |
LS |
3,00,000 |
300,000 |
| 12. |
Deep tube well
with submersible pump with storage tank, pumping
and distribution system |
1 |
5,00,00 |
5,00,000 |
| 13. |
Mini transport
vehicle (3 Wheelers) |
1 |
3,00,000 |
3,00,000 |
| 14. |
Fire extinguisher
5 kg capacity |
2 |
20,000 |
40,000 |
| 15. |
Testing equipments |
LS |
|
2,00,000 |
| 16. |
Computer colour
matching equipment (optional) |
1 |
25,00,000 |
25,00,000 |
|
Total
|
88,40,000 |
| (iii) Other Fixed Assets |
(Rs.) |
| (a) Erection and installation |
8,84,000 |
| (b) Office furniture |
5,00,000 |
| (c) Pre-operative expenses |
3,00,000 |
|
Total
|
16,84,000 |
| Total Fixed Capital (i) + (ii)
+ (iii) |
3,48,24,000 |
B. Working Capital
(i) Staff and Labour Wages
| Sl. No. |
Designation |
Nos. |
Rate (Rs.) |
Amount (Rs.)
|
| 1. |
G. Manager |
1 |
30000 |
30,000 |
| 2. |
Finance and Accountant
|
2 |
|
15,000 |
| 3. |
Computer Operator
|
1 |
20,000 |
20,000 |
| 4. |
Sales, marketing,
administrative and |
6 |
|
50,000 |
| 5. |
Peon |
2 |
3500 |
7,000 |
| 6. |
Watchman |
4 |
3500 |
14,000 |
|
Total (i)
|
1,26,000 |
| (ii) Production
Staff |
| 7. |
Dyeing Master
01 no. and shift supervisors 03 nos. |
|
|
36,000 |
| 8. |
Skilled Workers |
12 |
5,000 |
60,000 |
| 9. |
Semi-skilled Workers |
15 |
3,000 |
45,000 |
| 10. |
Lab. Chemists
and Attendant |
6 |
|
30,000 |
| 11. |
Boiler Attendant |
4 |
4000 |
16,000 |
| 12. |
Electrician |
3 |
4000 |
12,000 |
|
Total
|
1,99,000 |
|
Total (i) + (ii)
|
3,25,000 |
| Perquisites@ 22% |
72,000 |
|
G. Total
|
3,97,000 |
(iii) Raw Material (per month)
| Sl. No. |
Description |
Unit |
Qty. |
Rate/ unit (Rs.) |
Amount (Rs.) |
| 1. |
Caustic Soda |
Kgs. |
1500 |
35 |
53,000 |
| 2. |
Soda ash |
Kgs. |
5500 |
20 |
1,10,000 |
| 3. |
Sodium silicate |
Kgs. |
2500 |
10 |
25,000 |
| 4. |
Lisopal |
Kgs. |
750 |
150 |
1,13,000 |
| 5. |
Bleaching Powder |
Kgs. |
3,000 |
20 |
60,000 |
| 6. |
Hydrochloric acid |
Kgs. |
8,000 |
8 |
64,000 |
| 7. |
Glabour's salt |
Kgs. |
800 |
10 |
8,000 |
| 8. |
Common salt |
Kgs. |
1000 |
3 |
3,000 |
| 9. |
Optical whitening
agent |
Lit. |
225 |
140 |
32,000 |
| 10. |
Hydrogen peroxide |
Lit. |
1200 |
20 |
24,000 |
| 11. |
Sulphuric acid |
Lit. |
2500 |
10 |
25,000 |
| 12. |
Acetic acid |
Lit. |
750 |
75 |
56,000 |
| 13. |
Dye fixing agent |
Kgs. |
750 |
150 |
1,13,000 |
| 14. |
Dyes of different
shades |
Lump-sum |
|
|
1,00,000 |
|
Total
|
7,86,000 |
| (iv) Utilities |
(Rs.) |
| Electricity bill 37.5 x 25
x 4 x 0.8 x 24 |
72,000 |
| Water charges |
10,000 |
| Fuel Coal/furnace oil |
100,000 |
| Fuel for vehicle |
8,000 |
|
Total
|
1,90,000 |
| (v) Other Contingent Expenses |
(Rs.) |
| (a) Rent |
- |
| (b) Postage/stationery |
5,000 |
| (c) Repair and maintenance |
22,000 |
| (d) Transport/travelling charges |
30,000 |
| (e) Insurance |
19,000 |
| (f) Telephone bills |
10,000 |
| (g) Miscellaneous |
50,000 |
|
Total
|
1,34,000 |
| (vi) Total Recurring Expenses
(per month) |
11,10,000 |
| (vii) Total Working Capital
for 3 months |
33,30,000 |
C. Total Capital Investment
| (i) Machinery and equipment |
Rs. 3,48,24,000 |
| (ii) Working capital for 3
months |
Rs. 33,30,000 |
|
Total
|
Rs. 4,81,54,000 |
Machinery
Utilisation
Capacity utilisation is considered as 75% of installed
capacity.
Financial Analysis
| (1) Cost of Production (per
year) |
(Rs.) |
| Recurring expenses |
1,33,20,000 |
| Depreciation on machinery @
10% |
6,14,000 |
| Depreciation on office furniture,
computor and testing equipments @ 20% |
6,40,000 |
| Depreciation on civil construction
@ 5% |
5,90,000 |
| Interest on total investment
@ 12% |
57,78,000 |
|
Total
|
2,03,02,000 |
(2) Turnover (per year)
| Processing Charges |
Qty. Kgs. |
Rate/Kg. |
Amount (Rs.) |
| Bleaching Charges |
4,50,000 |
25.75 |
1,15,86,000 |
| Dyeing charges |
4,50,000 |
32.90 |
1,48,05,000 |
|
Total
|
2,63,91,000 |
| (3) Net Profit (per year) |
60,89,000 |
| (4) Net profit ratio (Net profit/Turnover
(per year) |
23.07% |
| (5) Rate of return on investment
(Net profit/Total capital investment) |
12.64% |
(6) Break-even Point
| Fixed Cost |
(Rs.) |
| Depreciation |
18,44,000 |
| Rent |
- |
| Interest on capital investment |
57,78,000 |
| 40% of wages of staff and labour |
19,05,000 |
| 40% of other expenses |
6,43,000 |
| Insurance |
2,28,000 |
|
Total
|
1,03,98,000 |
| B.E.P. |
= |
Fixed Cost ×
100
-------------------- |
| |
|
Fixed cost + Profit |
| |
|
|
| |
= |
1,03,98,000 ×
100
---------------------- |
| |
|
1,03,98,000 + 60,89,000 |
| |
|
|
| |
= |
63.07% |
Addresses
of Machinery and Equipment Suppliers
1. M/s. Gangan Mech. Works
28-B, Industrial Area,
Ludhiana-141003.
2. M/s. Ludhiana Dyeing Machinery Works
3064, St. No. 3, Ganesh Nagar,
Ludhiana-141003.
3. M/s. Paradise Engg. Corpn.
302, Industrial Area-A,
Ludhiana-141003.
4. M/s. Dynamic Engg. Corpn.
Dionic Chambers,
50, Rani Jhansi Road,
New Delhi-110055
5. M/s. Data Colour
3061/4, Lucky Lanes,
Andheri East,
Mumbai.
Raw Material Suppliers
1. M/s. Rangila Dyes Co.
Chauri Sarak,
Ludhiana.
2. M/s. Crescent Dye Industries
Chauri Sarak,
Ludhiana.
3. M/s. Sarjeevan Dyes Mfr. Co.
Industrial Area-A,
Ludhiana-141003.
4. M/s. ICI (India) Ltd.
P. B. No. 107,
Himaltane House,
New Delhi-110001.
Contact for more information:
Information Manager
TIMEIS Project
E-mail: timeis@ficci.com

|