|
|
|
 |
Technology |
|
Asbestos Pressure Pipes and
Fittings
|
Product Code
|
:
|
94407 |
| Quality
and Standards |
:
|
IS
1592 : 1988 |
| Production
Capacity: Qty. |
: |
6000
MT (per annum) |
| Uploaded
on |
: |
3 January 2006 |
Introduction
Asbestos pressure Pipes
and Fittings are manufactured out of Chrysotile
Asbestos (Long Fibre Asbestos) and ordinary
Portland Cement ranges in different length
and diameter. Generally these are 4 meter
in length and 80 degree and 80mm in diameter
and fittings of various designs are 90 degree
and above, single equal function and double
equal function.
Market Potential
In the light of economic
liberalization, all round development is taking
place in the country. There is a very good
demand of AC pressure pipes and fittings in
the Government department and domestic market.
These pipes and fittings are extensively used
for the drainage of rainwater and irrigation
purpose. With the upsurge in the building
construction and housing, the demand has further
increase. There is good scope for setting
up the industry for the manufacture of these
products.
Basis and Presumptions
It is considered that
the unit will work for 300 days in a year
on two shift basis:
i. The efficiency of the plant has been considered
at 80% of installed capacity. In case of pressure
pipe unit, the bottleneck operation in pipe-moulding
machines.
ii. The unit may achieve a production of 60%
and 70% in the first and second year of its
operation.
iii. Labour and wages has been taken as per
minimum wages prescribed by the authorities
or more as per the market trend.
iv. An average rate of interest is taken @
12% for the working and fixed capital requirements.
v. The promoter is expected to put in 25%
margin money.
Implementation Schedule
| Sl.
No. |
Activity |
Period
|
| Starting |
|
Completion |
| 1. |
Survey for collection
of date in respect of demand, raw materials,
power and fuel,availability of technology,
pollution control etc. |
0 |
to |
2nd month |
| 2. |
Arrangement for margin
money |
2nd |
to |
3rd month |
| 3. |
Preparation for project
document and registration |
2nd |
to |
3rd month |
| 4. |
Financial assistance |
4th |
to |
6th month |
| 5. |
Selection of site
and development of land |
4th |
to |
6th month |
| 6. |
Make shifts office |
|
to |
7th month |
| 7. |
Clearance for pollution
Control |
3rd |
to |
6th month |
| 8. |
Electricity, Water
etc. |
4th |
to |
6th month |
| 9. |
Construction/modification |
7th |
to |
10th month |
| 10. |
Identification/selection
of machines |
|
to |
5th month |
| 11. |
Placement of orders
(Machines) |
|
to |
6th month |
| 12. |
Transportation and
installation of Machines and equipments
|
10th |
to |
11th month |
| 13. |
Selection of raw
material and placement of orders |
|
to |
9th month |
| 14. |
Receipt of material |
10th |
to |
11th month |
| 15. |
Installation of Laboratory
equipments |
9th |
to |
10th month |
| 16. |
Trial production |
|
|
12th month |
Technical Aspects
Process of Manufacture
a) Raw Materials
Asbestos is a naturally
occurring mineral mainly consisting of magnesium
silicate in fibrous form. There are two principal
types of asbestos, chrysotile, soft and coiled
serpentine variety which is greenish white
and Amphibole occurring in five different
forms. For the manufacture of AC pressure
pipes chrysotile (long fibre) asbestos and
ordinary portland cement is used the ratio
of 10:90 (approx.) depending upon the quality.
The availability of this type of Asbestos
is very less in the country. Generally imported
Asbestos from Brazil is used by the industry.
It produces diverse characteristics in combination
with cement such as resistance to fire, corrosion
humidity and is very stable, durable and possessed
considerable strength.
b) Ordinary Portland Cement
Pipes are manufactured
on pipe moulding machine and mandrels. The
mixture of cement and asbestos is pumped into
mandrel which rotates in between two rollers.
The feeding of slurry is done by manual operation.
After required thickness the pipe is taken
out with the help of trolley lined with cloth.
In case of pressure pipe, this is again kept
on other rollers for giving more strength
and kept in shed for 24 hours for setting
or hardening and them kept in curing tanks
filled with water for 14- 15 days. During
the manufacturing process vacuum is created
inside the mould so that desire thickness
of the mixture of asbestos and cement can
be deposited. The water which comes out through
the holes of mandrels is recycled. The composition
varies with the length of pipe. By and large
asbestos to cement ratio is 1:9. However,
ratio varies depending upon quality. Imported
variety chrysolite is used for the manufacture
of A.C. Pressure pipes and fittings. Generally
10-15% of asbestos is used for manufacture
of the products. These pipes are 4 meters
long with diameter ranging from 80mm to 300mm.
Quality Control and Standards
The products have to
be tested according to IS 1582: 1989 issued
by Bureau of Indian Standards.
| Production
Capacity (per annum) |
| Quantity |
: 6, 000 MT. |
| Value |
: Rs. 3, 37, 18, 500 |
| |
|
| Motive Power |
125 HP |
Pollution Control
To avoid health hazard
to workers due to air borne, asbestos and
cement, it is recommended to install dust
collecting system and adopt safe work practice.
The following are the simple recommendations
to control dust in this industry:
a) it is recommended
to prohibit smoking inside the working place.
b) The floor should be well built. The clearing
of floors at various places is recommended
by water mopping
c) A centralized dust collecting system of
suitable capacity should be provided with
extension of ducts fitted with control valves
to the following machines:
i) Fibre opening machine with suitable charging
platform hood and water mist spray system.
ii) Turbo mixer with a hood and charging platform.
iii)Pipe cutting machine provided with a hood
and spray system.
d) Carrying of slurry with basket to pipe
forming machine should be replaced by a pump
and flexible pipe system.
e) Workmen working in the area with potential
to release asbestos dust should wear mask
while working.
f) The used bags should be reversed in wet
condition in a water tank and rinsed. The
water can be used in mixer with the help of
pump at frequent intervals. The empty bags
free from fibres can be disposed off.
Working hoods with dust
cover may be provided for moulding and should
be suitably connected with suctions devices.
Financial Aspects
A. Fixed Capital
| (i) Land and Building |
(Rs.)
|
| Land-6.000 sq. mtrs. @
Rs. 4000 per sq. mtrs. |
24,00,000
|
| Built-up area Office and
Stores 100 sq. mtrs: @ 10,000 per sq. mtrs,
boundry wall, gates, roads etc. |
1,25,00,000
|
| Shed for Plant 1500 sq.
mtr. @ 9,000 per sq. mtrs. |
1,08,00,000
|
|
Total
|
2,57,00,000
|
(ii) Machinery and Equipments
| Production unit |
Qty. |
(Rs.)
|
| Pipe making machine along
with mandrels of 80mm dia and 4 meter long with
30HP motor |
INo. |
80,00,000
|
| Vacuum Pump with 30HP motor |
INo. |
5,00,000
|
| Mixer with 10 HP motor |
2No. |
8,00,000
|
| Misc. items like pipe racks
line etc. |
Lot |
5,00,000
|
| Lab and Testing equipments |
|
8,00,000
|
| Pollution control Equipments
like dust collector, asbestos handling and storing
equipment, Raw water system, D,G, Set and Misc.
utility equipment |
|
30,00,000
|
| Curing tanks size 18' ×
16 × 5 @Rs. 1,00,000 each |
10 |
10,00,000
|
| Cost of moulds for pipe
of 22 Nos.@ Rs. 2,00,000 each |
|
44,00,000
|
| Installation and electrification
charges @ 10% |
|
19,00,000
|
| Cost of fittings |
|
10,00,000
|
| Office furniture and equipment |
|
5,00,000
|
| Pre-operative expenses |
|
4,00,000
|
|
Total
|
2,28,00,000
|
| Total Fixed Capital |
(Rs.)
|
| 1. Land and Building |
2,57,00,000
|
| 2. Machinery and Equipments |
2,28,00,000
|
|
Total
|
4,85,00,000
|
B.
Working Capital (per month)
(
i ) Staff and Labour (per month)
| Particulars |
Nos. |
Salary (Rs.) |
Amount (Rs.)
|
| Technical Manager and marketing
and sales team |
3 |
50,000 |
50,000
|
| Supervisor |
1 |
10,000 |
10,000
|
| Accountant cum cashier
and finance professional |
3 |
|
40,000
|
| Skilled workers |
10 |
5,000 |
50,000
|
| Moulders |
5 |
5000 |
25,000
|
| Un-skilled workers |
10 |
3500 |
35,000
|
| Clerk cum Typist |
2 |
5,000 |
10,000
|
| Peon |
2 |
3,000 |
6,000
|
| Watchman |
3 |
4,000 |
12,000
|
|
Total
|
2,38,000
|
| Perquisites
@ 20% |
52,000
|
|
Total
|
2,90,000
|
| (ii) Raw
Material (per month) |
(Rs.)
|
| a. Ordinary
Portland Cement 230MT @ Rs. 4000 |
9,20,000
|
| b. Crytobailite
Asbestos 25MT @ Rs. 80,000 |
20,00,000
|
| c. Lubricants |
20,000
|
|
Total
|
29,40,000
|
| (iii) Other Contingent
Expenses (per month) |
(Rs.)
|
| Postage and Stationery |
5,000
|
| Consumable store |
10,000
|
| Sales and marketing expenses |
1,50,000
|
| Repair and Maintenance |
33,000
|
| Transport Charges |
25,000
|
| Adminstrative expenses |
1,50,000
|
| Insurance |
20,000
|
| Misc. Expenses |
15,000
|
|
Total
|
4,08,000
|
| (iv) Utilities (per
month) |
(Rs.)
|
| 1. Power 125HP (125 ×
75 × 16 × 25) @ Rs. 5 per unit |
1,88,000
|
| 2. Water |
5,000
|
|
Total
|
1,93,000
|
| (v) Recurring
cost (per month) (i+ii+iii+iv) |
Rs. 38,31,000
|
| (vi) Recurring
cost for 3 months Rs. |
Rs. 1,14,93,000
|
| C. Total Capital
Investment |
| Land and Building |
Rs. 2,57,00,000
|
| Plant and Machinery |
Rs. 2,28,00,000
|
| Working capital
for 3 months |
Rs. 1,14,93,000
|
|
Total
|
Rs. 5,99,93,000
|
Machinery Utilisation
80% utilisation has taken
into consideration.
Financial Analysis
| (1) Cost of Production
(per year) |
(Rs.)
|
| Raw material |
3,52,80,000
|
| Staff and labour |
34,80,000
|
| Other Contingent Expenses |
4,08,000
|
| Utilities |
23,16,000
|
| Depreciation on building
@ 5% |
11,65,000
|
| Depreciation on machinery
@ 10% |
14,60,000
|
| Depreciation on moulds,
fixtures and furniture @ 20% |
9,80,000
|
| Interest on total capital
investment @ 12% |
71,99,000
|
|
Total
|
5,22,88,000
|
| (2) Annual Turnover |
(Rs.)
|
| AC Pipes assorted Sizes
(Pressure non pressure) |
6000MT
|
| Sale realisation @ 12,400
per MT |
7,44,00,000
|
| Profit and Loss Account
7,44,00,000 - 5,22,88,000 |
2,21,12,000
|
(3) Profit Percentage
(per annum)
| |
= |
Profit per year x 100
-----------------------
Total Sale |
| |
|
|
| |
= |
2,21,12,000
-----------------x 100
7,44,00,000 |
| |
|
|
| |
= |
29.72% |
| |
|
|
| (4)
Return on Total Investment |
| |
= |
Profit per annum x 100
--------------------------
Total Investment |
| |
|
|
| |
= |
2,21,12,000
-----------------x 100
5,99,93,000 |
| |
|
|
| |
= |
36.85% |
| (5) Break-even Point |
(Rs.)
|
| Total depreciation |
36,05,000
|
| 40% of staff and labour |
13,92,600
|
| 40% of other expenditure/consumable |
19,58,000
|
| Insurance |
2,40,000
|
| Interest on total capital |
71,99,000
|
|
Total
|
1,43,94,600
|
|
B.E.P.
|
Fixed
cost x 100
---------------------- |
| |
Fixed cost
x 100 |
| |
|
| |
1,43,94,600
x 100
---------------------------
1,43,94,600 + 2,21,12,000 |
| |
|
|
|
39.43% |
Addresses of Machinery
and Equipment suppliers
1. M/s. Jaipur Asbestos
New Sanganer Road,
Sodala, Jaipur
2. M/s. T.S. Enterprises
E-416, Road No. 14,
V. K. I. Area
Jaipur 302 013
3. M/s. Ganesh Engineering Company
Ajmer Road,
Beawar 305 901
Testing Equipment
Suppliers
1. M/s. Joshi Scientific
Corporation
59, Bapu Gam Road,
Mumbai
2. M/s. Idento (P) Ltd.
Idento House,
336, Mitn. Road,
Mumbai
Raw Material
Suppliers
1. M/s. Sneh International
3052, Section D,
Pocket 3, Basant Kunj,
New Delhi
2. M/s. Andhra Pradesh Mining Corpn.
Hyderabad (AP)
3. M/s. Easthfield Product
5A/6th Floor,
New Excelsion Building,
Bastion Road,
Mumbai 400 001
4. M/s. Dutta Brog. and Co.
N. S. Road,
Kolkata
Contact for more information:

|
|
|